Project:
BEATRICE POWER PROJECT, Gage County, NE
Project Owner:
Nebraska Public Power District
Completion Date: Jan. 2005
Utility Engineering (UE) and TIC formed a Joint Venture partnership
for this EPC 2-on-1 combined cycle, 229 MW General Electric (GE)
7EA combustion turbine project. UE provided all detailed civil/structural,
mechanical, electrical and controls balance of plant (BOP) engineering
including all procurement specifications.
In addition, UE provided field engineer services during checkout,
start-up and performance testing. Construction began in May 2003
and Provisional Acceptance occurred January 7, 2005.
Services Performed:
- Plant layout
- Detailed BOP engineering
- Procurement specifications
- Field engineering
- Commissioning
- As-built documentation